All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Wainwright School District 9
IFCB Posted : Sep 24, 2024
Bid Deadline : Tuesday, Nov 5, 2024

Questions Due By : Thursday, Oct 3, 2024
Applicant Address : Wainwright, OK 74468
IFCB ID : 250000659

IFCB Requirements :

·        Before the listed deadlines, all Questions and Bids must be submitted using the on-line IFCB system. Bids submitted before the bid deadline outside of this system will be disqualified. If the system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission. The applicant reserves the right to request and obtain bids outside of the website system if the bid deadline has passed and zero or one bid is received (the intent for this is to follow USAC guidance on obtaining cost-effective bids).

·       For all requested services and/or products listed on this IFCB: proposals that include generic/encyclopedic price lists will be considered non-responsive and will be disqualified. SPAM and/or robotic responses will not be considered valid bid responses and will be disqualified from consideration.

 

·        Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·        Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·        By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·        Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·        Contracts must not prohibit SPIN changes.

 

·        Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·        Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·        All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·        All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·        If there is a request for Internal Connections (Category Two) equipment, or Category One equipment listed on this IFCB the applicant will accept bids for functionally equivalent equipment.

 

·        E-rate rules require applicants to evaluate the cost of eligible goods and services, and to cost-allocate out the amount for ineligible services from their funding request. If your company will be bidding internet access service, please identify the amount to be cost-allocated out for the ineligible services – email service, web hosting, content filtering, or other bundled ineligible services.

·        INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

·        INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

·        INTERNET ACCESS DISQUALIFICATION FACTOR: Bidders who are not eligible to provide OUSF support will be disqualified. By placing a bid for these services, the bidder agrees to file the completed OUSF affidavit within 90 days of the start of service (applicant agrees to complete their portion in a timely fashion after the request for completion by the winning bidder).

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire hardware Project A, Project B, Project C, Project D, Project E or Project F.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

·        DISQUALIFICATION FACTOR BMIC: Service providers are required to bid an entire Project G and/or Project H.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

·        DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·        DISQUALIFICATION FACTOR BMIC: Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.


Services and Equipment Requested :

Category One:

Internet Access - District currently has 100 Mb bandwidth and would like to increase to 500 Mb. The terminating address for this circuit is located at Wainwright Elementary School - 115 E. Walnut, Wainwright, OK 74468. Bids should include pricing for 100 Mb, 200 Mb, 300 Mb, 400 Mb and 500 Mb and include a leased managed router.

 

NOTE: Applicant will accept any technologies bid. It is our intention to meet all OUSF Fair and Open Competitive Bidding requirements. If you are a NECA/tariffed company, bids for your tariffed rates are allowed. If any of the specified bandwidth speeds are not a tariffed/NECA rate, please bid the closest rate you have available, within the limits of the bandwidth range specified on the 470.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Bidders who are not eligible to provide OUSF support will be disqualified. By placing a bid for these services, the bidder agrees to file the completed OUSF affidavit within 90 days of the start of service (applicant agrees to complete their portion in a timely fashion after the request for completion by the winning bidder).

Category Two:

VOLUNTARY SITE VISIT

Vendors wishing to bid on internal connections can attend a voluntary site visit either September 26, 2024, or October 1, 2024, both at 9:00am. Vendors will meet at 115 E. Walnut, Wainwright, OK 74468. Vendors will check in with the front office – Shelby Frazier, Secretary.

 

INTERNAL CONNECTIONS

 

PROJECT A – 1 YEAR LICENSING ARUBA SOLUTION

Installation needed for the entire project. The district will move forward with Project A, Project B, Project C, Project D, Project E OR Project F.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

HP Aruba 24 port PoE with 1 year licensing

UPS/Battery Backup

2

Tripplite

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

PROJECT B – 3 YEAR LICENSING ARUBA SOLUTION

Installation needed for the entire project. Installation needed for the entire project. The district will move forward with Project A, Project B, Project C, Project D, Project E OR Project F.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

HP Aruba 24 port PoE with 3 year licensing

UPS/Battery Backup

2

Tripplite

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

PROJECT C – 5 YEAR LICENSING ARUBA SOLUTION

Installation needed for the entire project. Installation needed for the entire project. The district will move forward with Project A, Project B, Project C, Project D, Project E OR Project F.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

HP Aruba 24 port PoE with 5 year licensing

UPS/Battery Backup

2

Tripplite

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

PROJECT D – 1 YEAR LICENSING RUCKUS SOLUTION

Installation needed for the entire project. Installation needed for the entire project. The district will move forward with Project A, Project B, Project C, Project D, Project E OR Project F.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

Ruckus 24 port PoE with 1 year licensing

UPS/Battery Backup

2

Tripplite

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

PROJECT E – 3 YEAR LICENSING RUCKUS SOLUTION

Installation needed for the entire project. Installation needed for the entire project. The district will move forward with Project A, Project B, Project C, Project D, Project E OR Project F.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

Ruckus 24 port PoE with 3 year licensing

UPS/Battery Backup

2

Tripplite

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

PROJECT F – 5 YEAR LICENSING RUCKUS SOLUTION

Installation needed for the entire project. Installation needed for the entire project. The district will move forward with Project A, Project B, Project C, Project D, Project E OR Project F.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

Ruckus 24 port PoE with 5 year licensing

UPS/Battery Backup

2

Tripplite

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire hardware Project A, Project B, Project C, Project D, Project E or Project F.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

 

BASIC MAINTENANCE OF INTERNAL CONNECTIONS:

BMIC PROJECT G – ARUBA SOLUTION

The district will move forward with either BMIC project G or H not both.

The district would like a block of 5 hours per month for the support of eligible equipment.

 

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

Aruba 24 port PoE

UPS/Battery Backup

2

Tripplite

 

BMIC PROJECT H –RUCKUS SOLUTION

The district will move forward with either BMIC project G or H, not both.

The district would like a block of 5 hours per month for the support of eligible equipment.

 

Cabling

Approximately 2

Cabling drops for switches. Termination/upgrade and management

Racks

4

No preference – 12U Rack

Racks

4

No preference – 1500 series rack mount

Switches

2

Ruckus 24 port PoE

UPS/Battery Backup

2

Tripplite

 

DISQUALIFICATION FACTOR BMIC: Service providers are required to bid an entire Project G and/or Project H.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR BMIC: Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.


There is an additional document associated with this IFCB. Please click the buttons to download the document.

WAINWRIGHT_C2_COVER_PAGE.pdf
2025_C2_Bidding_Instructions27.pdf

You need to login / register to upload bid.

Questions Received with Applicant Answers   ( Ask Questions? )