All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Dardanelle School District
IFCB Posted : Oct 18, 2024
Bid Deadline : Friday, Nov 29, 2024

Questions Due By : Sunday, Oct 27, 2024
Applicant Address : Dardanelle, AR 72834
IFCB ID : 250002906

IFCB Requirements :

·         Before the listed deadlines, all Questions and Bids must be submitted using the on-line IFCB system. Bids submitted before the bid deadline outside of this system will be disqualified. If the system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission. The applicant reserves the right to request and obtain bids outside of the website system if the bid deadline has passed and zero or one bid is received (the intent for this is to follow USAC guidance on obtaining cost-effective bids).

·        For all requested services and/or products listed on this IFCB: proposals that include generic/encyclopedic price lists will be considered non-responsive and will be disqualified. SPAM and/or robotic responses will not be considered valid bid responses and will be disqualified from consideration.

 

·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·         Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·         Contracts must not prohibit SPIN changes.

 

·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·         All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·         If there is a request for Internal Connections (Category Two) equipment, or Category One equipment listed on this IFCB the applicant will accept bids for functionally equivalent equipment.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT A ONLY: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.


Services and Equipment Requested :

Category One:

Hot Spots & Service for Home Internet Use - The district is requesting bids for 205 hot spot devices including 205 monthly service plans.  The district is requesting service plans with a minimum 3Mb bandwidth and maximum 20Gb bandwidth.  Please include any installation, activation, configuration costs in your pricing.  Please include separate pricing for any CIPA/filtering costs. 

 

 

Category Two:

INTERNAL CONNECTIONS

IC Project A – Firewall Licensing

No installation needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Firewall Service and Components

1

1 Year Fortigate License (UTP) for 601F Fortigate

 

NOTE: We are requesting firewall licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

COMPATIBILITY REQUIREMENT:

Fortigate license must be compatible with existing Fortigate 601F.

 

IC Project B – UPS

No installation needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

UPS/Battery Backup

2

Preferred Eaton 6000VA 208/220/240v Network controllable UPS – Double Conversion

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT A ONLY: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 


There is an additional document associated with this IFCB. Please click the buttons to download the document.

2025_C2_Bidding_Instructions69.pdf
DARDANELLE_C2_COVER_PAGE1.pdf

You need to login / register to upload bid.

Questions Received with Applicant Answers   ( Ask Questions? )




What is the serial number of the FortiGate 601F?

Answer:

Our serial Number is: FG6H1ETB20907070

In regards to the UPS: Is any 120V output required from the UPS? If 120V is required, how many 5-15/20R outlets are required on the UPS? Is a maintenance bypass module required with the UPS? What is the full load runtime required from the UPS? In what type of rack will the UPS units be installed; 4-post, 2-post, etc?

Answer:

No 120V outlets are required. The maintenance bypass module is not required but will be taken into consideration as part of the bid, if offered. There is no minimum or maximum full load runtime; however, we anticipate this being between 2 and 10 minutes. This will be installed in a 4-port rack.