All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Okemah School District 26
IFCB Posted : Dec 9, 2024
Bid Deadline : Thursday, Jan 16, 2025

Questions Due By : Thursday, Dec 19, 2024
Applicant Address : Okemah, OK 74859
IFCB ID : 250008751

IFCB Requirements :

·         Before the listed deadlines, all Questions and Bids must be submitted using the on-line IFCB system. Bids submitted before the bid deadline outside of this system will be disqualified. If the system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission. The applicant reserves the right to request and obtain bids outside of the website system if the bid deadline has passed and zero or one bid is received (the intent for this is to follow USAC guidance on obtaining cost-effective bids).

·        For all requested services and/or products listed on this IFCB: proposals that include generic/encyclopedic price lists will be considered non-responsive and will be disqualified. SPAM and/or robotic responses will not be considered valid bid responses and will be disqualified from consideration.

 

·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·         Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·         Contracts must not prohibit SPIN changes.

 

·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·         All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·         If there is a request for Internal Connections (Category Two) equipment, or Category One equipment listed on this IFCB the applicant will accept bids for functionally equivalent equipment.

 

·         E-rate rules require applicants to evaluate the cost of eligible goods and services, and to cost-allocate out the amount for ineligible services from their funding request. If your company will be bidding internet access service, please identify the amount to be cost-allocated out for the ineligible services – email service, web hosting, content filtering, or other bundled ineligible services.

·         INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

·         INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

·         INTERNET ACCESS DISQUALIFICATION FACTOR: Bidders who are not eligible to provide OUSF support will be disqualified. By placing a bid for these services, the bidder agrees to file the completed OUSF affidavit within 90 days of the start of service (applicant agrees to complete their portion in a timely fashion after the request for completion by the winning bidder).

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT A & PROJECT B ONLY: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A, Project B, Project C, Project D and/or Project E.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

  

·         DISQUALIFICATION FACTOR BMIC: Service providers are required to bid the entire maintenance project.  Bids for individual components of Project F will be disqualified.

·         DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR BMIC: Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.


Services and Equipment Requested :

Category One:

Internet Access – 1 GB internet access. The terminating address for this circuit is located at 704 East Date, Okema, OK 74859. The district is seeking 1 GB bandwidth however, will accept bids up to 5GB.

 

E-rate rules require applicants to evaluate the cost of eligible goods and services, and to cost-allocate out the amount for ineligible services from their funding request. If your company will be bidding internet access service, please identify the amount to be cost-allocated out for the ineligible services – email service, web hosting, content filtering, or other bundled ineligible services.

INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Bidders who are not eligible to provide OUSF support will be disqualified. By placing a bid for these services, the bidder agrees to file the completed OUSF affidavit within 90 days of the start of service (applicant agrees to complete their portion in a timely fashion after the request for completion by the winning bidder).

 

Internet Access – DSL, 105x10 Mbps with a leased modem. The terminating address for this connection is located at 516 N 7th Street, Okemah, OK 74859.

 

E-rate rules require applicants to evaluate the cost of eligible goods and services, and to cost-allocate out the amount for ineligible services from their funding request. If your company will be bidding internet access service, please identify the amount to be cost-allocated out for the ineligible services – email service, web hosting, content filtering, or other bundled ineligible services.

INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

Category Two:

VOLUNTARY SITE VISIT

Vendors wishing to bid on internal connections can attend a voluntary site visit on December 18th, 2024 between the hours of 8am – 1:30pm. Vendors will meet at 204 W Date Street, Okemah OK 74859. Vendors will check in with Ronald Vick.

 

INTERNAL CONNECTIONS

IC Project A – WAPs

Installation and configuration needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Wireless Access Points

31

Ubiquiti U7-Pro

 

NOTE: We are requesting WAP licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

COMPATIBILITY REQUIREMENT:

Equipment must be compatible with existing Unifi network.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT A & PROJECT B ONLY: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

 

IC Project B – Switches

Installation and configuration needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Antennas, Connectors and Related Components

2

Ubiquiti UACC-OM-MM-1G-D-2

Antennas, Connectors and Related Components

1

Ubiquiti UACC-OM-MM-10G-D-2

Switches

12

Ubiquiti USW-PRO-48-POE

Switches

2

Ubiquiti USW-PRO-24-POTE

 

NOTE: We are requesting switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

COMPATIBILITY REQUIREMENT:

Equipment must be compatible with existing Unifi network.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT A & PROJECT B ONLY: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

 

IC Project C – UPS

Installation and configuration needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

UPS/Battery Backup

4

TrippLite SMART1500RM2U

UPS/Battery Backup

1

TrippLite SU1500RTXLCD2U

UPS/Battery Backup

1

TrippLite BP48RT

 

 

IC Project D – Cable Runs

Installation and configuration needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

5

CAT6 Cabling runs

 

 

IC Project E – Firewall/Caching Server

No installation or configuration needed.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Caching Server

1

K12USA Secure School

Firewall Service and Components

1

K12USA Secure School

 

NOTE: We are requesting caching and/or firewall licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT A & PROJECT B ONLY: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A, Project B, Project C, Project D and/or Project E.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

 

BASIC MAINTENANCE OF INTERNAL CONNECTIONS:

BMIC Project F – Firewall/Caching Service

The District would like a manufacturer’s support contract for these items

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Caching Server

1

K12USA Secure School

Firewall Service and Components

1

K12USA Secure School

 

DISQUALIFICATION FACTOR BMIC: Service providers are required to bid the entire maintenance project.  Bids for individual components of Project F will be disqualified.

DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR BMIC: Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.

 


There is an additional document associated with this IFCB. Please click the buttons to download the document.

2025_C2_Bidding_Instructions176.pdf
OKEMAH_C2_COVER_PAGE1.pdf

You need to login / register to upload bid.

Questions Received with Applicant Answers   ( Ask Questions? )




DIA -Dedicated Internet Access How many public routable IPV4 addresses do you need? What type of handoff do you need from our Network Interface Device? Ethernet 850 nm Multimode Fiber 1310 Single Mode Fiber Do you have at least 4 Rack Units of space available for Vyve to mount our customer premise equipment? Can you provide 2 AC outlets providing 100-240 VAC, 50-60 Hz, 0.5-0.3 Amps? Do you have an existing Network Address Translation device (router, firewall) that Vyve will hand off to? What is the approximate distance in feet from where our NID will be placed to your NID (router, switch, firewall)?

Answer:

DIA -Dedicated Internet Access How many public routable IPV4 addresses do you need?

    /29 block (6 usable addresses)

What type of handoff do you need from our Network Interface Device?

    1g copper.  If bidding over 1g use 10g SR fiber handoff

Do you have at least 4 Rack Units of space available for Vyve to mount our customer premise equipment?

     Yes

Can you provide 2 AC outlets providing 100-240 VAC, 50-60 Hz, 0.5-0.3 Amps?

     Yes

Do you have an existing Network Address Translation device (router, firewall) that Vyve will hand off to?

     Yes

What is the approximate distance in feet from where our NID will be placed to your NID (router, switch, firewall)

    15 ft