All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Hutto ISD
IFCB Posted : Nov 22, 2024
Bid Deadline : Friday, Jan 3, 2025

Questions Due By : Sunday, Dec 1, 2024
Applicant Address : Hutto, TX 78634
IFCB ID : 250006725

IFCB Requirements :

·         Before the listed deadlines, all Questions and Bids must be submitted using the on-line IFCB system. Bids submitted before the bid deadline outside of this system will be disqualified. If the system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission. The applicant reserves the right to request and obtain bids outside of the website system if the bid deadline has passed and zero or one bid is received (the intent for this is to follow USAC guidance on obtaining cost-effective bids).

·        For all requested services and/or products listed on this IFCB: proposals that include generic/encyclopedic price lists will be considered non-responsive and will be disqualified. SPAM and/or robotic responses will not be considered valid bid responses and will be disqualified from consideration.

 

·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·         Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·         Contracts must not prohibit SPIN changes.

 

·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·         All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·         If there is a request for Internal Connections (Category Two) equipment, or Category One equipment listed on this IFCB the applicant will accept bids for functionally equivalent equipment.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist. Vendors that submit bids that include these manufacturers will have their bids disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire Project.  Bids for individual components of a single project will be disqualified.


Services and Equipment Requested :

PLEASE NOTE:  If you previously bid on 470/IFCB #250004511 for “Project C – Hutto HS and Nadine Johnson re-cabling” you must resubmit your bid under this new 470/IFCB #250006725.

CATEGORY TWO

INTERNAL CONNECTIONS

The District is requesting bids for the re-cabling of Hutto High School, including new single-mode fiber to be run from each IDF back to the MDF, as the current fiber does not support moderns speeds.  All cabling must be CommScope certified.  Maps are available to download.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Cabling

15

SM fiber runs

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist. Vendors that submit bids that include these manufacturers will have their bids disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire Project.  Bids for individual components of a single project will be disqualified.


There is an additional document associated with this IFCB. Please click the buttons to download the document.

Hutto_C2_COVER_PAGE1.pdf
2025_C2_Bidding_Instructions139.pdf
Fiber_runs.pdf

You need to login / register to upload bid.

Questions Received with Applicant Answers   ( Ask Questions? )




Are you no longer requesting a quote for the 2000 Copper runs?

Answer:
That is correct.

Has the requirement for CommScope been removed for the Fiber? If so, which brand would you like us to utilize?

Answer:
We would still like CommScope certified fiber runs. 

Have you removed the copper cabling from this project? Some additional questions: Is there a breakdown of cable drops (copper/fiber) needed per location? Is there a breakdown of devices (switches, APs, UPS, etc.) and models per location? Are there floorplans available for each location, preferably with the network closets and indoor/outdoor AP locations marked up? Are these all 1-1 swaps with existing devices, or will some of the APs also need cable drops? If new APs and drops are needed, are those new locations called out at each school? Is certification required for the copper as well? If yes, which manufacturer certification? Will this project occur during normal business hours, or afterhours/weekends to avoid network downtime? What is the number of existing AP swaps (outdoor vs indoor)? What is the number of new AP installs (outdoor vs indoor)? What is the number of copper cable drops? How many numbers of fiber cable drops? Thank you

Answer:

Have you removed the copper cabling from this project? 
             Yes
Is there a breakdown of cable drops (copper/fiber) needed per location? 
             No copper anymore. The 15 single-mode fiber runs are on the previously provided drawings.
Is there a breakdown of devices (switches, APs, UPS, etc.) and models per location? 

  • UPS
    • Hutto High School
      • 1 L6-30 compatible
      • The rest, 5-20
    • Howard Normal Elementary
      • 3 L6-30 compatible
  • Switches
    • Hutto High School
      • 1 ICX 7550 w/ routing licensing
      • 8 ICX 8200 multi-gig
      • The rest, standard ICX8200 as counted in the IFCB
    • Howard Norman Elementary
      • 1 ICX 7550 w/ routing licensing
      • 3 ICX 8200 multi-gig
      • The rest, standard ICX8200 as counted in the IFCB
    • Lee Martinez Elementary
      • 1 ICX 7550 w/ routing licensing
      • 7 ICX 8200 multi-gig
      • The rest, standard ICX8200 as counted in the IFCB
  • WAPs
    • Ruckus SZ controller compatible suggestions welcome. Currently looking at the R670.

Are there floorplans available for each location, preferably with the network closets and indoor/outdoor AP locations marked up?
             We don’t have those available at this time. This project will only be replacing most, not all, of the existing WAPs
 Are these all 1-1 swaps with existing devices, or will some of the APs also need cable drops? 
             No new cable drops. Switches at Hutto High and Howard Norman will be swaps. Lee Martinez is a new campus and will be an initial install. We are not installing WAPs at Lee Martinez, just providing them for the general contractor.
If new APs and drops are needed, are those new locations called out at each school? 
             N/A, not needed.
Is certification required for the copper as well? If yes, which manufacturer certification? 
             N/A
Will this project occur during normal business hours, or afterhours/weekends to avoid network downtime? 
             Summer break, ideally.
What is the number of existing AP swaps (outdoor vs indoor)? 
             They’re all existing, the counts should be on the IFCB.
What is the number of new AP installs (outdoor vs indoor)? 
             No new installs.
What is the number of copper cable drops? 
             N/A
How many numbers of fiber cable drops?
             15 single-mode horizontal cable runs, CommScope.