All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Celina Indep School District
IFCB Posted : Dec 2, 2024
Bid Deadline : Monday, Jan 13, 2025

Questions Due By : Wednesday, Dec 11, 2024
Applicant Address : Celina, TX 75009
IFCB ID : 250007534

IFCB Requirements :

·         Before the listed deadlines, all Questions and Bids must be submitted using the on-line IFCB system. Bids submitted before the bid deadline outside of this system will be disqualified. If the system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission. The applicant reserves the right to request and obtain bids outside of the website system if the bid deadline has passed and zero or one bid is received (the intent for this is to follow USAC guidance on obtaining cost-effective bids).

·        For all requested services and/or products listed on this IFCB: proposals that include generic/encyclopedic price lists will be considered non-responsive and will be disqualified. SPAM and/or robotic responses will not be considered valid bid responses and will be disqualified from consideration.

 

·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·         Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·         Contracts must not prohibit SPIN changes.

 

·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·         All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·         If there is a request for Internal Connections (Category Two) equipment, or Category One equipment listed on this IFCB the applicant will accept bids for functionally equivalent equipment.

 

·         DISQUALIFICATION FACTOR CATEGORY ONE NETWORK EQUIPMENT: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

·         DISQUALIFICATION FACTOR CATEGORY ONE NETWORK EQUIPMENT: Service providers are required to bid the entire hardware project.  Bids for individual components, or bids that do not include all of the requested items for the project of the project will be disqualified.

 

·         DISQUALIFICATION FACTOR CATEGORY ONE NETWORK EQUIPMENT: Vendors must complete and include the C1 Cover Page with their bid. Bids received without the cover page will be disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire hardware project.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.


Services and Equipment Requested :

Category One:

Category 1 Network Equipment-

Installation and configuration needed.

Type of Equipment

Quantity Vendor Should Bid

Preferred Make/Manufacturer

Switch

3

HPE Aruba Networking CX 6300M 24-port SFP+ and 4-port SFP56 Switch -

JL658A

Switch component

6

HPE Aruba Networking X371 12VDC 250W 100-240VAC Power Supply – JL085A

Switch component

6

  Power Cord - U.S. localization – JL085A ABA

Transceiver

8

HPE Aruba Networking 50G LR 10km SMF Transceiver – S0V65A

DAC Cable

8

HPE Aruba Networking 10G SFP+ to SFP+ 3m Direct Attach Copper Cable – J9283D

 

DISQUALIFICATION FACTOR CATEGORY ONE NETWORK EQUIPMENT: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

DISQUALIFICATION FACTOR CATEGORY ONE NETWORK EQUIPMENT: Service providers are required to bid the entire hardware project.  Bids for individual components, or bids that do not include all of the requested items for the project of the project will be disqualified.

 

DISQUALIFICATION FACTOR CATEGORY ONE NETWORK EQUIPMENT: Vendors must complete and include the C1 Cover Page with their bid. Bids received without the cover page will be disqualified.

 

Category Two:

INTERNAL CONNECTIONS

No cabling drops needed. Bids should include installation and configuration.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Antennas, Connectors and Related Components

24

HPE Aruba Networking X372 54VDC 1050W 110-240VAC Power Supply – JL087A

Antennas, Connectors and Related Components

24

HPE Power Cord - U.S. localization – JL087 ABA

Antennas, Connectors and Related Components

8

HPE Aruba Networking 10G SFP+ LC LR 10km SMF Transceiver – J9151E

Antennas, Connectors and Related Components

5

HPE Aruba Networking AP-MNT-MP10-B Campus AP mount bracket kit (10-pack) type B: suspended ceiling rail, flat 15/16 – Q9G69A

Antennas, Connectors and Related Components

8

HPE Aruba Networking AP-270-MNT-V2 Outdoor AP Short Arm Pole/Wall Mounting Bracket – JW053A

Antennas, Connectors and Related Components

40

Oberon - Right Angle Wall Mount -

1007-FPDome

Cabling

10

HPE Aruba Networking 10G SFP+ to SFP+ 3m Direct Attach Copper Cable – J9283D

Switches

12

HPE Aruba Networking CX 6200M 36G 12SR5 Class6 PoE 4SFP+ Switch – R8Q71A

UPS/Battery Backup

2

Eaton - 2200VA UPS SMART LITHIUM ION LIFEPO4 2U -

SMART2200RM2UL

UPS/Battery Backup

12

Eaton - 1500VA UPS SMART LITHIUM ION LIFEPO4 2U -

SMART1500RM2UL

Wireless Access Points

7

HPE Aruba Networking AP-635 (US) Tri Radio 2x2 Wi-Fi 6E Internal Antennas 5-pack Campus Access Point - S3J36A

Wireless Access Points

3

HPE Aruba Networking AP-635 (US) Tri-radio 2x2 802.11ax Wi-Fi 6E Internal Antennas Campus AP - R7J28A

Wireless Access Points

4

HPE Aruba Networking AP-655 (US) Tri-radio 4x4 802.11ax Wi-Fi 6E Internal Antennas Campus AP - R7J39A

Wireless Access Points

8

HPE Aruba Networking AP-675 (US) Tri Radio 2x2 Wi-Fi 6E Internal Omni-Directional Outdoor AP - S0P50A

Wireless Access Point Licensing

50

HPE Aruba Networking Central AP Foundation 5-year Subscription E-STU -

Q9Y60AAE. Licensing for WAPs listed above.

 

NOTE: We are requesting WAP and/or switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

COMPATIBILITY REQUIREMENT:

All WAPs must be compatible with existing Aruba Central

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire hardware project.  Bids for individual components, or bids that do not include all of the requested items for the project will be disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

 


There is an additional document associated with this IFCB. Please click the buttons to download the document.

2025_C2_Bidding_Instructions157.pdf
CELINA_C1_COVER_PAGE1.pdf
CELINA_C2_COVER_PAGE2.pdf

You need to login / register to upload bid.

Questions Received with Applicant Answers   ( Ask Questions? )




Are the ceilings for the Wireless AP's drop ceilings or will a lift be needed? Thank you

Answer:

Majority of them are reachable with a standard 8ft ladder, however there might be a few locations where a lift may be needed. The district will not provide a lift.